Data center (Azraelito/Wikimedia Commons)
A grid operator covering much of the eastern U.S. proposed a plan that could help states make data centers pay for power line upgrades.
PJM Interconnection asked the Federal Energy Regulatory Commission (FERC) on Monday to approve the plan, which would also halve the expected review period for proposed power plants and big electricity users, the grid operator said. The proposal is not final, and the operator asked regulators to rule on it within 120 days.
The plan would “give states transparent access to the costs of transmission improvements driven by data centers, as directed by FERC, empowering states to bill Large Loads for those costs,” PJM said in its announcement. Large Loads are customers drawing 50 megawatts or more at one site, the filing states.
“Under the proposal, the intent is that large loads/data centers bear the costs of the transmission upgrades they drive, not traditional customers,” PJM spokesman Jeff Shields said in a statement to the Daily Caller News Foundation.
Shields said PJM “does not control how those costs are allocated.”
PJM told FERC that it would put the costs of those upgrades, and what drove them, in one place on its website that anyone can search. States would then be able to use their power over retail rates to decide if certain customers should pay them, according to the filing.
Utilities that own the power lines get to propose how to split up and recover those costs, PJM wrote in the filing.
Data centers account for 30 of the 32 gigawatts of peak demand growth that PJM’s 2025 forecast projects between 2024 and 2030, the filing states. The high-voltage grid it runs serves more than 67 million people in the District of Columbia and 13 states, wholly or partly, the grid operator’s website says.
PJM sent FERC a separate proposal Monday that would require data centers to stay on the grid when disturbances hit rather than switching over to backup power, the grid operator said.
On July 22, nearly 3.9 gigawatts of data centers dropped off utility power at once and switched to their own generators. PJM said in announcing the proposal that it was the biggest such event in its history.
“PJM operators were able to react so that no customers were in imminent danger of losing power,” Shields, the grid operator’s spokesman, said.
PJM asked regulators in its filing to rule on the ride-through proposal by Jan. 15, 2027. If FERC approves it, the rules would start Jan. 16, 2027, for data centers and similar computing sites that use 50 megawatts or more. Sites that are already running would get one year to comply, according to PJM.
All content created by the Daily Caller News Foundation, an independent and nonpartisan newswire service, is available without charge to any legitimate news publisher that can provide a large audience. All republished articles must include our logo, our reporter’s byline and their DCNF affiliation. For any questions about our guidelines or partnering with us, please contact [email protected].